WSRT stop-day activities April 30, 2019
Coordinator | Teun Grit | roadmin@astron.nl |
---|---|---|
Software Support | Arno Schoenmakers | schoenmakers@astron.nl |
Science, Operations and Support | Vanessa Moss | moss@astron.nl |
Observer | TBD | observer@astron.nl |
Actions
- Operator will stop Apertif software befor 08:00
- Update & reboot of all systems (incl LCU's and both data writers) (Teun and Jasmin)(since UB14 is out of support it will be the last update)
- Jenkins: update plugins (TBD)
- Artefactory: update to latest version
Note:
- ✔ Test update of lcu-rt0 befor the stop-day (firday)
- Stop Virtualbox on alta2 befor you start updating / rebooting (do we touch it? )
- Put Ubuntu repository GPG keys in place before stop-day
- Migration of ZFS-DKM to ZFSK-KMOD (wop63,wop75,wop85)
- Do not update ZFS replica's until all works
- ✔ Spacewalk VM will be updated before stop-day
Results
The results can be found in this Google Spreadsheet
Have a look at the minutes of the review meeting
The stop-days procedure can be found on this page