WSRT stop-day activities Dec, 2020
Coordinator | Walter | roadmin@astron.nl |
---|---|---|
Software Support | ||
Science, Operations and Support | Manu | orru@astron.nl |
Observer | ask Observing team | observer@astron.nl |
Actions
- Operator will stop Apertif software before 08:00
- Update & reboot (do not reboot before network change) of all systems (incl LCU's and both data writers) (Walter and Jasmin)System Overview
Note:
- Spacewalk VM will be updated before stop-day (Walter)
- Test update of lcu-rt0,dop70,wop78 before the stop-day (Walter)
- Test update of hypervisor wop85 (ZFS/KVM) before the stopday (Walter)
- Stop Virtual-box on alta2 before you start updating / rebooting (Jasmin)
- Network change (ip/subnet) (before reboot)(Jasmin)
Results
The results can be found in this Google Spreadsheet
The stop-days procedure can be found on this page