WSRT stop-day activities March 12, 2019
Coordinator | Teun Grit | roadmin@astron.nl |
---|---|---|
Software Support | Arno Schoenmakers | schoenmakers@astron.nl |
Science, Operations and Support | Vanessa Moss | moss@astron.nl |
Observer | Paul van Dijk | observer@astron.nl |
Actions
- Operator will stop Apertif software befor 08:00
- Arno can stop MCU
- Update & reboot of all systems (incl LCU's and both data writers) (Teun and Jasmin)
- CentOS 7 systems will be updated to 7.6 and rebooted using SpaceWalk (Jasmin & Teun)
- SLES11_SP4 systems will be updated by Teun and Jasmin
- We will update lcu-rt2 first, then test it and then update the rest of the lcu's
- Jasmin will update & reboot ALTA systems (Dwingeloo) Please keep Roy de Goei informed.
- Jenkins: update plugins (TBD)
Note:
- ✔ Test update of lcu-rt0 befor the stop-day
- Test update of hypervisor wop61 before th stopday (DMZ kernel module)
- Stop Virtualbox on alta2 befor you start updating / rebooting (do we touch it? )
- Put Ubuntu repository GPG keys in place before stop-day
- Do not update ZFS replica's until all works
- ✔ Spacewalk VM will be updated before stop-day
GPG key update:
sudo apt-key adv --keyserver keyserver.ubuntu.com --recv-keys <list of keys>
Results
The results can be found in this Google Spreadsheet
Have a look at the minutes of the review meeting
The stop-days procedure can be found on this page