This is an old revision of the document!
LOFAR Technical Status Meeting
Date | 18 – 19 May 2009 |
---|---|
Location | ASTRON, Dwingeloo |
Agenda
Presentations
Day 1, Mon 18 May 2009
- R. Vermeulen: Welcome
- M. Wise: Introduction and Timelines
- C. Vogt: Roll-out status
- A. Gunst: Hardware status
- M. Brentjens: Bands, Beams, and Bits
- C. Broekema: CEP Performance
- H. Holties: Archive Status
- G. de Bruyn: Calibration Status
- R. Nijboer: Imaging Sensitivities
- M. Wise: LOFAR Observing Modes
- R. Nijboer: Imaging Pipeline
- J. Hessels: Pulsar Pipeline
- A. Horneffer: VHECR Pipeline
Day 2, Tue 19 May 2009
- A. Polatidis: Proposal Support
- M. Wise: Commissioning Plans
- G. de Bruyn: MSSS Specifications
- J. Conway: Long-baseline Issues
- H. Rottgering: Surveys
- J. Anderson: Magnetism
- G. de Bruyn: EoR
- R. Fender: Transients
- B. Stappers: Pulsars
- A. Horneffer: Cosmic Rays
- G. Mann: Solar and Space Weather